Heisenberg for product managers: Why you cannot have a fast and certain ship date

"When will it be done?"

I have had this conversation with product teams many, many times. As a product manager, you want things to happen sooner. You don't want to be wrong — especially when you are communicating dates externally or promising something to a customer.

But there is a problem with asking your engineering teammates to be really sure about a delivery date. You might think that forcing them to commit means you will get the work sooner. In practice, the date can move further into the future, and the work will take longer.

We have talked about this with the product team at Aha! for a few years now and tailored our internal process around it. But human nature keeps coming back. It is really easy to ask for a date. And as soon as you do, the dynamic changes.

I think of this as the uncertainty principle of engineering estimation.

How soon, and how certain?

Maybe you have heard of Heisenberg's uncertainty principle. The basic idea is that the more accurately we know the position of a particle, the less accurately we can know its momentum (or vice versa). We cannot know both things accurately at the same time. The more certainty we have about one value, the less certainty we have about the other.

I think there is an analogy here with product management and engineering estimation when it comes to dates.

As a product manager, you care about two things: How soon will the work be done? And how accurate is the estimate of when it will be done?

But the more certain you want to be about when something will come, the further into the future that date needs to be.

It is hard to estimate how long something will take in software development. An engineer might think it will be done around a particular date, but perhaps it will be early, or perhaps it will be late. To be more confident that they will hit the deadline, they need to give you a date further in the future.

You then see that date moving out and say, "You need to be really, really sure we are going to ship it by that date." And the engineer thinks, "Now I have to pad it even more, because you want me to be really confident."

The date becomes an anchor

There is another factor here. People fill up the time available once a date exists.

Even if they are not procrastinating or wasting their time, they will find other things to do. "It is not due for two weeks. We can squeeze in this other bit of functionality, or I can polish this and make it a little better."

The date becomes a self-fulfilling prophecy. Even if the engineer padded it to be really sure, adding more work means they are taking risks with that date anyway.

This happens even in productive, healthy teams. All the great engineers I know hate having nothing to do. They would much rather deliver something, have it off their plate, and move on to the next interesting problem to solve.

But if they are nearing completion and there is still time, there is always more that could be done. Scope can increase from either side. The engineer sees an opportunity to improve what they have built. The product manager sees the work is ready, notices there is a week left, and asks for more functionality. Both are adding complexity because the date is still further out.

You might think that is good because you get more functionality by the date. But perhaps you would have been better off shipping it earlier — even if you shipped something smaller.

What are we trying to achieve?

Our objective as a team is to ship things as soon as we possibly can. The sooner we get the work in front of customers, the sooner they get value from what we have built. And the sooner we learn from our work so we can improve it and take the next step.

That might not be true in every environment. Perfection is critical in some, and shipping something less perfect earlier is less desirable. But in typical software engineering for B2B and B2C businesses, we want things as soon as we can get them.

One way to overcome this is to have a trusting environment. By trust, I mean that the product team trusts the engineering team to deliver things as efficiently and quickly as it can.

Having a date can feel like a security blanket. It gives you confidence. Not having one is uncomfortable. But you have to ask yourself: Does it actually change the reality? Do things get delivered on the deadline, or does the deadline slip as you get closer to it?

You cannot have blind trust. You have to know your team. Trust is built over time. If your engineering teammates deliver things quickly, you build up trust and an expectation that they will continue to do that in the future.

We consciously recognized the uncertainty principle at Aha! a few years ago and tailored our process around it. We did not remove dates entirely. Product managers still put general timing on the roadmap. What we moved away from was asking engineering to commit to a ship date once the work is prioritized.

Instead, engineers share a possible date, which is the earliest the work could be done if everything goes well. They update it as they go and let the product manager know when work is at risk or getting bigger. Then, the product manager and engineer can adjust scope, priority, or timing.

Launch planning waits until the code is live or close enough that we can share a date with confidence.

We found that things started to get delivered faster — not slower.

An estimate is not a deadline

It is not unreasonable to ask, "How long do you think this will take?" Before we start work on features, we need to understand how much investment will be required to prioritize them. Most of that investment is engineering time.

But this is the trap people fall into. They ask for an estimate, the engineer gives an estimate, and then they take today plus the estimate and say, "Great. Here is our deadline."

That is the mistake. One is an estimate of what you think the work will take. The other is a deadline. This is not an argument for not estimating. It is an argument for not using the estimate to set a deadline.

Of course, there are circumstances where the date really does matter. There are external forcing factors we have no choice over, and things have to be done by that date.

In those circumstances, we need to operate differently. There is a separate set of techniques around triage and incremental development so we can ship on that date with whatever is completed. What I have been describing here is our standard operating procedure where there are no external date factors.

You might choose to have dates. That is fine. You just have to understand how this trade-off applies to the way you use them.

If the work goes smoothly and gets done quickly, we want to benefit from that. Ship it when it is done. Don't stretch it out to reach the deadline.